Task Dependencies

Tasks & scheduling3 min read

Dependencies control how one task's dates relate to another. Create links in Gantt or edit them in the task detail panel.

TypeMeaningTypical use
FS (Finish → Start)Successor starts when predecessor finishesDefault handoff between trades
SS (Start → Start)Both start togetherParallel work from the same milestone
FF (Finish → Finish)Both finish togetherCoordinated completion
SF (Start → Finish)Successor finishes when predecessor startsRare; specialist sequencing

Lag and lead

  • Lag — delay after the dependency logic (e.g. +2d after predecessor finishes).
  • Lead — overlap (negative lag, e.g. -1d to start before predecessor finishes).

Set lag/lead in task details when you select the dependency link.

  1. Open the task in Gantt or list.
  2. Find Dependencies / predecessors in the detail sheet.
  3. Change type or lag, or delete the link.