Punch List
Punch List is the defect register on Job → Construction. Each punch item has a status, assignee, priority, optional due date, location, and photos.
Job → Construction → Punch List register
desktop
When to use this
Use punch list for defects and handover items that need an owner and a close-out.
Use Daily log for the day's record. Use RFIs when you need an answer, not a fix.
Before you start
- You can write punch items on the plot or standalone job.
- On a development, pick the plot first. Punch items do not live on the scheme.
- Optional: keep room labels in Settings → Library → Locations.
Open the register
Job → Construction → Punch list for the full list. On a phone, My Work → Add punch item captures one without opening the job first.
Add the punch item
Title, location, description, priority, due date, assignee, and photos.
Add punch item with location and photos
mobile
Move status
Typical path: Open → In progress → Ready for inspection → Closed. Rejected sends it back for rework. You can reopen a closed punch item.
From My Work → Punch list you see Assigned to me and Awaiting my review. That tab hides when both queues are empty.
What done looks like
- The defect is on the plot register with a photo and a location the rest of the team recognizes.
- The assignee sees it in My Work.
- Closed items stay on the job; they are not deleted.
Common mistakes
- Looking for every punch item on the job in My Work. My Work is your queue.
- Raising the punch item on the development.
- Titles like "extra" with no location or photo.
Email to a trade, public portal, and permissions
If the subcontractor does not use SiteHut:
- Open a punch item (or select several) and Send to subcontractor / Email selected to… (needs snags:manage).
- They get the details (reference such as SNAG-001, title, location, priority, status, due date, description). RFIs on the same share are listed too.
- If Include online portal link is on under Settings → Subcontractors → Snag & RFI emails, they can update status, upload photos, and comment without an account.
- Links expire after 30 days. Revoke from the punch item sheet. Portal comments land on Activity & Comments.
| Permission | Allows |
|---|---|
| snags:read | View the register |
| snags:write | Create and edit |
| snags:manage | Assign others, email, manage |
| snags:close | Close or reopen |
If Punch List is missing under Construction, you likely lack snags:read.